Little Sand Bay Construction Update – June 4th

  • National Park Service Visitor Center – The notice to proceed was just issued May 30, 2018 and the contractor, PDSI, is beginning to mobilize on site. The following are estimated dates for upcoming actions on the project: 1) June 4th– 8th – Mobilization, tree protection, asbestos abatement, tree/stump removal: 2) June 10th-15th – Demolition, sidewalk removal, start septic removal; and 3) June 18th – 22nd – Soil Remediation, sidewalk, asphalt removal, and backfill for demolition.
  • Twilite Shelter – The concrete footings and foundation walls were poured June 1st.